What are the biggest risks involved with trenchless crossing installations?
Pipelines installed using trenchless crossing methods face many engineering and geological challenges. Trenchless crossings are frequently used to install pipelines under rivers, highways, railway embankments, buildings or sensitive environmental habitats.
Unique risk factors come with the nature of the installation — almost all of the work performed below the earth’s surface, unseen from above. Though bore paths for projects are planned using reports derived from extensive geotechnical site investigation, survey, environmental studies and trenchless engineering design, there is always the inherent risk of encountering unforeseen and unavoidable circumstances underground.
Waterbody crossings — rivers, wetlands, creeks, shorelines, harbors etc. — are uniquely challenging. When crossing a watercourse or environmentally sensitive habitat it is necessary to understand its geotechnical, aquatic and environmental setting. Though horizontal directional drilling (HDD) is a commonly utilized crossing method, improper application of HDD, lack of information, or disregarding crossing-specific risks can lead to problems such as, delays, environmental damage, project cost overruns and ultimately, failure of the crossing attempt.
The risk of inadvertent drilling fluid release to the surface could have a negative environmental impact. Cleaning operations often involve heavy equipment in order to contain and clean drilling fluid in order to remove it as best as possible from the surface. Fluid release into a waterbody increases the turbidity of the water, and depending on which drilling fluid additives are used, may cause additional impact to flora, fauna and other aquatic life.
Significant unknown risks may arise from insufficient geotechnical investigation, improper planning, shortage of understanding site specific constraints, and lack of skilled engineering design or inexperienced construction execution. Subsurface risks are associated with the type and behavior of encountered soil and rock geology along the crossing path.
When crossing infrastructure, such as pipelines, utilities, roadways or railways, a lack of understanding the geotechnical setting or improper design of the crossing path below a surface obstacle could lead to excessive heave or settlement of the existing infrastructure causing potentially significant damage.
This can cause potentially dangerous circumstances such as sink holes, improper alignment of railway tracks, utility leaks, electrical short circuits, and building foundation impact.
In areas where subsurface infrastructure such as utilities, cables and pipelines already exist, it is important to know exactly where that infrastructure is in order to design a trenchless trajectory that avoids these subsurface obstacles.
A significant risk of an improperly planned trenchless crossing is cross-boring into an existing subsurface utility or pipeline. Cross-boring into an existing utility, may result in groundwater contamination, or other significant environmental and safety concerns, depending on the product conveyed by that pipeline, such as water, sewer, electrical or hydrocarbon.
Identifying the geotechnical conditions, environmental setting and site-specific constraints enables engineers and contractors to select the most appropriate trenchless method, equipment and tooling for a project.
Trenchless risk management requires a thorough understanding of potential problems that are site specific to each crossing on a project.
Appropriate risk mitigation measures can then be incorporated into the design and crossing details of the selected crossing method.
Tags
Written by Bertus Vos | Co-Founder and Principal Engineer, BlueFox Engineering

Bertus Vos is one of the co-founders and principal engineers at BlueFox Engineering. He holds a bachelor of engineering degree from the University of Alberta, and a master of business degree from the University of Fredericton.
More Q&As from our experts
- When should engineers take skin friction into account when writing mud specification for an HDD project?
- What are some of the new trenchless technologies being used to minimize carbon emissions?
- What's the future of UV cured-in-place pipe rehabilitation?
Related Terms
- Cross Bore
- Watercourse Crossing
- Geotechnical Investigation
- Inadvertent Returns
- Environmental Impact Assessment
- Crossing
- Geotechnical Information
- Geotechnical Report
- Desander
- Desilter
Related Articles

Daylighting to Avoid Cross Bores

Cross-Boring Can Be Deadly: Avoid Tragedy with These Important Work Practices

Trenchless Frac-out: How Do You Prevent It?

Trenchless Sewer Repair: To Trench or Not to Trench?
Don’t Miss the Latest From Trenchlesspedia!
Subscribe to our newsletter to get expert advice and top insights into every aspect of trenchless construction and rehabilitation. We create top educational content for and about the trenchless industry, insuring you have the knowledge you need for successful trenchless projects.
- Pullback Design in Horizontal Direction Drilling
- Everything You Need to Know About Hydrovac Trucks
- Fiber Installations: Your Ultimate Guide to Success
- The Ultimate Guide to Underwater Remotely Operated Vehicles and Robots
- A Mud Engineer's Ultimate Guide to Drilling Fluids
- Design Considerations - Roads Rivers and Rail: Structural Culvert Rehabilitation
- Buried Water & Wastewater Pipes: Installation, Replacement and Rehabilitation Tips and Techniques